Metal Systems
Call Today: (800) 445-8791
sales@equipmentcenters.com
Metal Systems - Custom Equipment Centers

EquipmentCenters vs. Conventional Buildings

A Metal Systems' Equipment Center (EC) is a prefabricated, modular electrical/instrument enclosure solution.  As a self-contained unit, it is a completely assembled structure manufactured entirely at the factory with a self supporting base frame and floor.  Typical equipment enclosed by the EC includes switchgear, motor control centers, relay panels, RTU's, instrument control panels, DCS systems, heat trace panels, UPS systems, variable speed drives, battery / DC systems and SCADA systems.
   
Table.1  A comparison of EC's  and conventional site built buildings.
Aspect Equipment Center Conventional Site Built Building
Tax, Depreciation & Commercial Issues Taxed and depreciated as equipment over 5 - 7 years, vs. Real Estate over 29 years. Treated as real estate improvement leading to higher tax schedule, much longer depreciation, building permits, progress inspection, bonding & insurance.
Major Electrical Equipment Pre-installed, wired and tested at factory before shipment Stored, handled, installed, wired and tested on site
Sourcing EC manufacturer is responsible for all equipment inside EC. Separate solicitation, analysis (and often) sourcing of switchgear, building, battery systems, bus duct, etc.
Design Engineering Complete package designed and engineered by EC manufacturer. Purchaser, or engaged third party, must design and engineer.
Future Portability Disconnect line and load cables and the EC is ready to move Not feasible
Future Expansion EC may be constructed with removable ends for quick and easy future expansion Extremely cumbersome, especially with block wall construction
Foundation Minimum foundation - piers or ring wall. Requires full slab foundation with relatively large stem walls and footings.
Construction Variety of materials including painted galvanized steel, stainless steel, and aluminum Typically, concrete block.
Base Self-supporting, allowing all equipment to be factory installed and leveled before shipment. Purchaser provides channel base and grouting for leveling all equipment on site.
Internal Wiring Factory wired complete with wiring schematics. Job-site interconnection of control wiring as well as major equipment.
Main Bus Coordinated by EC manufacturer. Purchaser coordinates the match up of main buses for different types of equipment.
Bus Duct from Transformers Checked for ease of assembly. Purchaser coordinates and assembles bus to switchgear in field for first time.
Grounding System Integral to EC. Must be planned and built into foundation.
External Connections Easily adaptable to overhead or underground conduit systems. Slab floor mandates detailed and exact conduit location; changes are difficult.
Testing EC is factory tested; customer can complete many pre-energization tests before installation.  Witness testing at one location. Each type of equipment is tested at different factories.  Witness testing requires more time and travel.
Changes Changes can be made after functional testing and inspection in controlled factory environment. Requires coordination between various trades, often after initial construction is complete.
Receiving, Handling, & Storage Arrives in single shipment, usually unloaded in one hour, can be stored indefinitely as integral unit, inherently protected against elements. Multiple component receiving often involves redundant handling for storage, trucking to intermediate locations, and protection during storage from pilferage or other loss, or lost time due to weather.
Electrical Load Cables Place the EC near the process being controlled for minimal Load cable runs Load cables may have to run excessively long lengths from the conventional building to the process being controlled
Installation Involves minimum number of crafts. Requires many crafts; i.e., carpenters, ironworkers, cement finishers, bricklayers, electricians-all with foremen and helpers.
Schedule Have the completed EC delivered the day it fits in your critical path Requires months of multiple trades and on site coordination
 
 


Equipment Centers Operator Centers Electrical Enclosures