|
A Metal Systems' Equipment Center (EC) is a prefabricated,
modular electrical/instrument enclosure solution. As a
self-contained unit, it is a completely assembled
structure manufactured entirely at the factory with a self
supporting base frame and floor. Typical equipment
enclosed by the EC includes switchgear, motor control
centers, relay panels, RTU's, instrument control panels,
DCS systems, heat trace panels, UPS systems, variable
speed drives, battery / DC systems and SCADA systems. |
|
|
|
|
|
Table.1 A comparison of EC's
and conventional site built buildings. |
|
Aspect |
Equipment Center |
Conventional Site Built Building |
|
Tax, Depreciation & Commercial Issues |
Taxed and depreciated as equipment over 5 - 7 years, vs.
Real Estate over 29 years. |
Treated as real estate improvement leading to higher tax
schedule, much longer depreciation, building permits,
progress inspection, bonding & insurance. |
|
Major Electrical Equipment |
Pre-installed, wired and tested at factory before shipment |
Stored, handled, installed, wired and tested on site |
|
Sourcing |
EC manufacturer is responsible for all equipment inside
EC. |
Separate solicitation, analysis (and often) sourcing of
switchgear, building, battery systems, bus duct, etc. |
|
Design Engineering |
Complete package designed and engineered by EC
manufacturer. |
Purchaser, or engaged third party, must design and
engineer. |
|
Future Portability |
Disconnect line and load cables and the EC is ready to
move |
Not feasible |
|
Future Expansion |
EC may be constructed with removable ends for quick and
easy future expansion |
Extremely cumbersome, especially with block wall
construction |
|
Foundation |
Minimum foundation - piers or ring wall. |
Requires full slab foundation with relatively large stem
walls and footings. |
|
Construction |
Variety of materials including painted galvanized steel,
stainless steel, and aluminum |
Typically, concrete block. |
|
Base |
Self-supporting, allowing all equipment to be factory
installed and leveled before shipment. |
Purchaser provides channel base and grouting for leveling
all equipment on site. |
|
Internal Wiring |
Factory wired complete with wiring schematics. |
Job-site interconnection of control wiring as well as
major equipment. |
|
Main Bus |
Coordinated by EC manufacturer. |
Purchaser coordinates the match up of main buses for
different types of equipment. |
|
Bus Duct from Transformers |
Checked for ease of assembly. |
Purchaser coordinates and assembles bus to switchgear in
field for first time. |
|
Grounding System |
Integral to EC. |
Must be planned and built into foundation. |
|
External Connections |
Easily adaptable to overhead or underground conduit
systems. |
Slab floor mandates detailed and exact conduit location;
changes are difficult. |
|
Testing |
EC is factory tested; customer can complete many
pre-energization tests before installation. Witness
testing at one location. |
Each type of equipment is tested at different factories.
Witness testing requires more time and travel. |
|
Changes |
Changes can be made after functional testing and
inspection in controlled factory environment. |
Requires coordination between various trades, often after
initial construction is complete. |
|
Receiving, Handling, & Storage |
Arrives in single shipment, usually unloaded in one hour,
can be stored indefinitely as integral unit, inherently
protected against elements. |
Multiple component receiving often involves redundant
handling for storage, trucking to intermediate locations,
and protection during storage from pilferage or other
loss, or lost time due to weather. |
|
Electrical Load Cables |
Place the EC near the process being controlled for minimal
Load cable runs |
Load cables may have to run excessively long lengths from
the conventional building to the process being controlled |
|
Installation |
Involves minimum number of crafts. |
Requires many crafts; i.e., carpenters, ironworkers,
cement finishers, bricklayers, electricians-all with
foremen and helpers. |
|
Schedule |
Have the completed EC delivered the day it fits in your
critical path |
Requires months of multiple trades and on site
coordination |